Completed loft master suite ensuite with exposed timber beams — Guernsey
All Projects
Renovation

Loft Master Suite Renovation

Bedroom and ensuite reconfiguration, structural works and bespoke joinery | Guernsey

Guernsey Approx. 8 weeks
Project Overview

A loft bedroom and ensuite completely reconfigured

This project involved the complete refurbishment and reconfiguration of a loft master suite, including both the bedroom and ensuite bathroom.

Our team carried out extensive structural alterations, forming new partition walls, strengthening the floor structure, installing insulation, and completing all first and second fix plumbing and electrical works. A new ensuite layout was created with a walk-in shower, waterproof tanking system, recessed shower niche, bespoke tiling and contemporary sanitaryware.

The bedroom was fully renovated with new ceilings, plasterboarding, skimming, recessed LED lighting, luxury flooring, bespoke fitted furniture and custom joinery. Existing structural timber beams were carefully retained and incorporated as feature elements, preserving the character of the property while delivering a bright, modern finish.

Main Works Completed

What we delivered on this loft master suite

Full strip-out and demolition
Structural alterations
Steel support installation and bespoke beam boxing
New stud partition walls
Floor strengthening and reconstruction
Insulation upgrades
Plumbing first & second fix
Electrical first & second fix
Recessed LED lighting
Waterproof shower tanking system
Bespoke recessed shower niche
Walk-in shower installation
Bathroom tiling
Bespoke fitted bedroom furniture
Carpentry and joinery
Plasterboarding and skimming
Luxury flooring
Decorating
Final snagging and completion
The Challenge

Working within an awkward loft structure

Loft spaces rarely give you square walls or spare height. Once the suite was stripped out, the floor structure needed strengthening, loads had to be supported with steels, and every millimetre of the new ensuite layout had to be planned around existing timber beams and sloping ceilings.

Rather than hide the original beams, we retained and boxed them as feature elements — keeping the character of the property while delivering a bright, contemporary suite.

Structural alterations underway in the loft master suite, Guernsey
Construction Process

From demolition to final decorative finishes

Every stage managed by our own team — no gaps between trades, no waiting around.

  1. 01

    Protection and set up

    Bedroom, landing and stairs protected with dust screens and floor coverings before any work began.

  2. 02

    Full strip-out and demolition

    Existing ensuite, partitions, linings, flooring and fittings removed and cleared from site.

  3. 03

    Structural alterations

    Openings reformed and the loft layout reconfigured to create a better bedroom and ensuite arrangement.

  4. 04

    Steel supports and beam boxing

    Steel supports installed where loads were transferred, with bespoke boxing built around beams.

  5. 05

    Floor strengthening

    Floor structure opened up, strengthened and reconstructed to take the new layout and finishes.

  6. 06

    New stud partitions

    New timber stud partition walls formed to set out the bedroom, ensuite and walk-in shower.

  7. 07

    First fix plumbing and electrics

    Hot and cold services, waste runs, circuits and lighting positions all first fixed within the new studwork.

  8. 08

    Insulation upgrades

    Thermal and acoustic insulation installed between studs and floor joists for warmth and privacy.

  9. 09

    Waterproof tanking

    Full tanking system installed to the shower area, with a bespoke recessed niche formed in the wall.

  10. 10

    Plasterboarding and skimming

    Ceilings and walls boarded and skimmed to a smooth, paint-ready finish throughout.

  11. 11

    Tiling and sanitaryware

    Bathroom tiling completed, walk-in shower installed and contemporary sanitaryware fitted.

  12. 12

    Second fix and joinery

    Second fix plumbing and electrics, recessed LED lighting, bespoke fitted furniture and custom joinery installed.

  13. 13

    Flooring and decorating

    Luxury flooring laid and the full suite decorated, with the original timber beams retained as feature elements.

  14. 14

    Snagging and handover

    Final snagging, full clean and handover of a finished, fully functional loft master suite.

Before — Strip out and structural works

Demolition, framing, tanking and boarding

Loft suite stripped out — partitions and linings removed ready for reconfiguration
Structural alterations underway with new openings formed and supports installed
Floor opened up for strengthening, insulation and new service runs
New timber stud partitions framed out with first fix electrics in place
Waterproof tanking boards installed to the new walk-in shower enclosure
Landing and suite plasterboarded ahead of skimming
Ensuite plastered and prepared, with the recessed niche formed in the wall
The original loft bathroom being stripped out beneath the exposed timber beams
Old shower tray, tiling and floor covering removed ready for the new layout
Partition framing and floor joists opened up for strengthening and new services
The suite stripped back to masonry and joists ahead of reconfiguration
Wedi tanking boards and recessed niche formed to the new shower enclosure
Fitted wardrobe recess plasterboarded and taped ready for skimming
Newly plastered walls and bespoke beam boxing with luxury flooring laid
Boxed structural post and freshly skimmed walls through to the landing
The original dated bathroom before works began, stripped back to bare boards
Existing tiling and panelling opened up to reroute services for the new layout
Wall tiling underway in the new ensuite over the tanked substrate
Full-height tiling completed and set out ready for the shower installation
Bespoke timber beam boxing machined on site to match the property's character
Self-levelling screed applied across the suite ready for the luxury flooring
After — The finished suite

A bright, modern loft master suite

The completed ensuite with retained timber beams as feature elements
Walk-in shower, luxury flooring and bright, modern finishes throughout
Finished ensuite with frameless glass shower, heated towel rail and exposed beams
Completed walk-in shower with rainfall head and recessed tiled niche
Finished master bedroom with bespoke fitted furniture and window seat storage
Bright, fully decorated bedroom with new flooring, lighting and fitted desk run
Second shower room finished in large-format stone-effect tiling
Completed bathroom with bath, screen and full-height tiling
Finished loft ensuite with walk-in shower and luxury flooring, Guernsey
Completed Result

A functional and beautifully finished master suite

From demolition through to the final decorative finishes, every stage of the renovation was completed by T.A. Construction. The result is a bright, modern loft master suite with a walk-in ensuite, bespoke fitted furniture, recessed LED lighting and luxury flooring — with the property's original timber beams retained as a feature throughout.